• Design build contract for an operational liquefied natural gas (LNG) facility that needed replacement of the existing truck scale for optimization purposes for weight and loading of tanker trucks. Project needed to be complete during fall and winter months during peak supply time for the need for liquefied natural gas (LNG) so scheduling and coordination were of the upmost importance
  • Demolition of existing mechanical truck scale and removal of existing foundation without any shutdown of the liquefied natural gas (LNG) facility daily operations of vaporization or liquefaction and all mechanical and electrical components included
  • Supply and installation of tri-axle model truck scale with instrumentation placed within new concrete pit and trench drain system. Trench grating and all associated concrete work build for H-20 load rating and the overall design of the drainage system placed the possibility of spill containment of liquefied natural gas (LNG) first and foremost
  • Site asphalt and utility work to interconnect the new scale with the liquefied natural gas (LNG) truck loading system. This work focused on the tanker tank ease of access to the new truck scale and a focus on the overall topography for proper drainage and secondary containment with the trench system
109