International Concourse Fueling System

Player and Company was entrusted with the expansion of the fuel storage and distribution system for the new Hartsfield Atlanta International Airport. On-time is a must for the country’s busiest airport.

This project, which had to be accomplished without interrupting service to the existing concourse, consisted of the installation of:

  • New 35,000 bbl fuel storage tank

  • 8000 gpm capacity pump station

  • Fuel control service building with a quality control laboratory

  • Installation of nearly two miles of 20 inch diameter underground fuel mains

  • 14 in. carbon steel aviation fuel piping to serve the airport’s extended cargo facility

All pipe joints were welded per ASME Code and x-rayed to ensure code compliance. All underground piping and catholically protected to provide a durable system.

 

International Concourse Fueling System

Player and Company was entrusted with the expansion of the fuel storage and distribution system for the new Hartsfield Atlanta International Airport. On-time is a must for the country’s busiest airport.

This project, which had to be accomplished without interrupting service to the existing concourse, consisted of the installation of:

  • New 35,000 bbl fuel storage tank

  • 8000 gpm capacity pump station

  • Fuel control service building with a quality control laboratory

  • Installation of nearly two miles of 20 inch diameter underground fuel mains

  • 14 in. carbon steel aviation fuel piping to serve the airport’s extended cargo facility

All pipe joints were welded per ASME Code and x-rayed to ensure code compliance. All underground piping and catholically protected to provide a durable system.

 